A reverse osmosis unit under one sink is a small job, but it has a clear order. You do not need to run the work yourself to watch for the steps that matter. Ask the installer to walk through each stage, and check that each one happened before you accept the job as done.

Start with the site check

Before any part goes in, the installer should confirm where the cold supply line is, whether the shutoff valve under the sink still turns and holds, where the drain connection will go, how much room there is for the tank and the housing, and whether the unit needs a power outlet. A shutoff valve that is stuck or leaks is a reason to stop and plan a repair first, not to bolt the unit on top of it.

Shut off, mount, and run the feed

The supply is turned off and the line is relieved before the feed adapter goes on. The mounting bracket and the filter housings should sit where the filters can be changed without taking the whole cabinet apart. The feed tubing should be cut square, pushed fully into each fitting, and kept clear of sharp edges and hot lines.

Connect the drain without trapping it

The drain connection should go on a drain line, not on a hot water pipe, and the tubing should run downhill so waste water flows freely. Watch for a drain that loops and holds water. A restricted drain makes the unit run longer and can cause it to waste more water than it should.

Check the storage tank before the faucet goes on

Ask the installer to check the storage tank's air pressure with a gauge, not by feel. A tank that is wrong will not deliver water the way the manufacturer intends, and that is far easier to fix before the faucet is mounted.

Mount the faucet and flush

The dedicated faucet goes in, its connection is tightened, and the unit is started. The installer should flush the system according to the manufacturer's instructions, then drain and refill the storage tank as the manual directs. Ask how long the flush takes, so you know when the first glass of water is safe to use.

Do a leak check you can repeat

Dry each fitting with a paper towel and look at it again after an hour, then again the next morning. The job is not finished until the connections stay dry through a full cycle of use.

Get the handoff in writing

Before you pay the final invoice, ask for the owner's manual, the filter replacement schedule, the name of the part numbers that need changing, and what to do if the drain runs continuously or the faucet drips. A written handoff turns the installer's visit into a record you can use later.